PROJECT NAME:

Refurbishment of schools in Kosovo

SECTOR:

Education

PROJECT VALUE:

Contract price (excluding PS and VAT/other taxes) 5,920,902.98 Euro Provisional Sum (Contingency) (15%) 888,135.45 Euro Total Contract Price, including the Provisional Sum 6,809,038.43 Euro

DURATION:

44 months/ Phase 1 in total 12 Months and Phase 2 in total 32 Months, including the Defect Liability Period

IMPLEMENTING PARTNER:

The Consortium led by Krapi Com SH.P.K. (XK), Kosovo

DIRECT BENEFICIARY:

(MEST) Ministry of Education, Science, and Technology, Kosovo

COVERAGE/IMPACT:

Municipalities: Prishtinë, Klinë, Kamenicë, Viti, Pejë and Podujevë

OVERALL OBJECTIVE:

To contribute to the developing quality-based, all-inclusive, and accountable pre- university education system in line with the best international practices.

PROJECT PURPOSES:

The Contract aims to prepare a detailed design and unit price works tender dossier and provide the complete Supervision set out in PRAG conditions and rules for the reconstruction works in several schools across Kosovo.

ACTIVITIES:

B1. Dardania, Pristina The site final activities include: - The flooring works. - The installation of new wooden and PVC doors. - Suspended ceilings work. - Painting of inside surfaces works. - Metal works. - The installation of slope platform lift. - Landscape works. - The installation of toilets fixtures and equipment. - The installation of heating appliances (radiators). - The installation of the substation. - The installation of water supply system in the boiler. - Air-condition for sports hall. - The installation of internal and outdoor lighting. - The installation of Sound system/ Public address and school. - The installation of Uninterrupted Power Supply (UPS). - The installation of Emergency supply (Diesel GENERATOR).

RESULTS:

The project is designed to refurbish six schools throughout Kosovo, and in this way improvethe existing school infrastructure.